Delayed

Officials refuse to reveal cost of new children’s hospital as opening delayed

David Gunning, of the NPHDB, said that even a hypothetical discussion on costs would prejudice the existing contract with construction company BAM.

OFFICIALS HAVE REFUSED to disclose the updated cost of building the new National Children’s Hospital, as it emerged that the opening date has been pushed back to the second half of 2024.

David Gunning, chief officer of the National Paediatric Hospital Development Board (NPHDB), said that even a hypothetical discussion on costs would prejudice the existing contract with construction company BAM.

The hospital, which is being built on the site of St James’s Hospital in Dublin, has been beset by spiralling costs that have escalated to 1.433 billion euro.

However, with no update on the projected costs, some TDs believe that could rise to two billion euro.

Sinn Fein’s David Cullinane said it is “disappointing” that Department of Health and hospital officials have not provided updated costs and clarity around timeframes for the project.

“It is disappointing that the statements from the department and Mr Gunning is that we won’t be in a position to get answers,” he added.

The contracted completion date for the hospital was August 2022; however the revised target date is now December 2023.

Mr Gunning said the temporary shutdown of the site due to Covid restrictions has delayed work by some 14 months.

He told the Oireachtas Joint Committee on Health it “more than likely” it will now open to the public in the second half of 2024.

“But that is conditioned by the risks that are currently in the construction sector, in terms of resource availability, and supply of necessary materials,” he said.
While Cabinet approved the more recent cost of 1.433 billion euro, that sum does not include a number of outstanding costs including construction inflation and hundreds of outstanding claims.

Today, the committee heard that the number of claims has now grown to 900.

29451d8c-6a48-45de-9ef8-dea97c4a785b David Gunning.

Mr Gunning said he could not provide the number of settled claims; however he later gave the committee updated figures.

“Fifteen of the hundreds of claims have come through conciliation, and, of those, nine have been agreed and the amount involved is about 2.5 million euros,” he added.

“Six of those we have issued a notice of dissatisfaction and they will go the High Court.”

Mr Cullinane was critical of the lack of information provided to the committee.

“There is a vacuum of accountability and transparency around this project,” he said.

“The estimated costs of the claims will be in the region of 200 million so it’s reasonable for me to ask what is settled and what is the cost of those claims.”

Cullinane later added: “It has been eight months since you last appeared and the update we have got is deeply unsatisfactory.

“This saga of building this hospital goes from one mess to the next.”

Fine Gael senator Martin Conway was also critical of the position taken by the board officials.

“The answers to the questions of Deputy Cullinane are nothing short of disgraceful,” he said.

Social Democrats co-leader Roisin Shortall said it is “really disappointing” that they could not give an update on estimated costs.

“At this stage, you are still working on a completely unrealistic figure of 1.433 billion,” she said.

Mr Gunning told Ms Shortall there is a moratorium on the dispute processes on all new and current claims.

“I get the impression that you are storing up a lot of costs and trouble for the future, and the issues are not being dealt with now,” Ms Shortall added.

“This project is going to continue to be a runaway train and nothing I have heard today gives me an assurance that is not going to be the case, that costs have been brought under control.”

2.41187761 An artist’s impression of the new National Children’s Hospital outside the building site as construction continues.

However, Mr Gunning said there is a “robust” system in place to defend the claims.

Solidarity-People Before Profit TD Gino Kenny asked Mr Gunning whether the board believes BAM is under-performing.

Mr Gunning replied: “We have an interesting relationship with the contractor. Having set off on this contract a number of years ago, the intention was to be collaborative and co-operative. In the middle of all the claims and commercial disputes that didn’t work out as planned.

“We are trying to recover that.

Author
Press Association
Your Voice
Readers Comments
26
This is YOUR comments community. Stay civil, stay constructive, stay on topic. Please familiarise yourself with our comments policy here before taking part.
Leave a Comment
    Submit a report
    Please help us understand how this comment violates our community guidelines.
    Thank you for the feedback
    Your feedback has been sent to our team for review.

    Leave a commentcancel