Children's hospital contractor seeking extra claims totalling more than €300 million
Six of the claims are more than €40 million, the committee was told.
Your contributions will help us continue to deliver the stories that are important to you
Six of the claims are more than €40 million, the committee was told.
The completion date for the project is also being pushed back further.
Taoiseach Micheal Martin appealed to the contractor and those working on building the hospital to get back on site.
The dispute relates around the validity of a contract to commence Phase B of construction of the Children’s Hospital without a design.
Paul Murphy said that “They are putting the workers in danger by continuing to operate at the site”.
One local councillor says local residents feel “under siege” from the constant construction work near their homes.
The Minister was responding to a statement by BAM that suggested it would pull out of the contract if the Government wanted.
Morgan stunner helps USWNT to 2-1 win over Germany in #SheBelieves Cup final.
Reus scores a thumper as Dortmund make it three wins from three.
The symbol used in the graffiti is the same as one seen painted with similar messages in Dublin city earlier this year.
WATCH: Crusaders’ Owen Franks smashes Bulls flanker Flip van der Merwe during last weekend’s Super Rugby clash.