Advertisement

We need your help now

Support from readers like you keeps The Journal open.

You are visiting us because we have something you value. Independent, unbiased news that tells the truth. Advertising revenue goes some way to support our mission, but this year it has not been enough.

If you've seen value in our reporting, please contribute what you can, so we can continue to produce accurate and meaningful journalism. For everyone who needs it.

Artist's impression of the Dublin MetroLink entrance at St Stephen's Green.
Metrolink

An Bord Pleanála to hold ‘oral hearing’ into €9.5 billion Dublin Metrolink project

The oral hearing will provide a platform for third parties to outline their concerns over aspects of the estimated €9.5 billion project.

AN BORD PLEANÁLA has confirmed that it is to stage an oral hearing into the estimated €9.5 billion Metrolink project for Dublin.

This follows the appeals board writing to parties confirming the oral hearing though a date for the oral hearing has yet to be set.

The MetroLink scheme is to comprise 16 new stations running from Swords to Charlemont and will carry 53 million passengers per annum.

In September of last year, Transport Infrastructure Ireland (TII) lodged its Draft Railway Order (DRWO) application with An Bord Pleanála seeking the planning go-ahead for the project and the appeals board has received 318 submissions on the DRWO.

Documentation lodged with the DRWO state that construction work is intended to commence in 2025 with an opening year of 2035.

The oral hearing will provide a platform for third parties to outline their concerns over aspects of the project.

State agency, the Office of Public Works (OPW) will be expected to clash with TII over the impact MetroLink will have on St Stephen’s Green.

In a submission, the OPW has expressed concern that the Dublin MetroLink project “would have a direct, severe, negative, profound and permanent impact” on the heritage value of St Stephen’s Green and contended that the risk of damage to St Stephen’s Green from a Dublin MetroLink station “is unacceptable”.

At the oral hearing, Trinity College Dublin (TCD) will also make the case that the route of the MetroLink under its Dublin campus be moved 61.5 metres westward to partly address its concerns over the project.

In a submission to An Bord Pleanala, consultants for TCD, Declan Brassil has stated that the current planned route of Metrolink and wholly inadequate mitigations measures proposed “have significant potential to constrain or sterilise Trinity’s existing and future core academic and research activities on the eastern part of the campus”.

The consultants have told the appeals board that in the event that TII fail to demonstrate that effective and proven mitigation measures can be implemented, then TCD “is left in the position where it requests that the Board refuses consent, or terminate Metrolink at a point north of Trinity’s campus”.

Already, a total of €300 million has been spent on Dublin’s various Metro projects to date with construction work yet to take place.

In. figures provided earlier this year by the Secretary General of the Dept of Transport, Ken Spratt stated that the spend on the current MetroLink to the end of March of this year is €115.3 million.

In his letter, Spratt said that a cost estimate for MetroLink of €9.5 billion is considered the most likely cost at this preliminary stage.

Your Voice
Readers Comments
59
This is YOUR comments community. Stay civil, stay constructive, stay on topic. Please familiarise yourself with our comments policy here before taking part.
Leave a Comment
    Submit a report
    Please help us understand how this comment violates our community guidelines.
    Thank you for the feedback
    Your feedback has been sent to our team for review.

    Leave a commentcancel