The project was initially approved by Mayo County Council Alamy Stock Photo

Man who won appeal overturning Mayo data centre hopes it 'represents change in thinking'

The data centre’s planning was overturned by An Coimisin Pleanála due to impact on the electricity grid and climate impact.

LAST UPDATE | 17 Sep

PLANS FOR A data centre in Co Mayo have been overturned by An Coimisiún Pleanála, partly because the operator was found to have failed to show there is “existing capacity” in the electricity grid to handle the added pressure of the system.

The contentious plans had been originally opposed by international best-selling author Sally Rooney, who warned of “wasteful consumption of electricity” that would push energy prices higher if approved.

The data centre was approved by Mayo County Council last year but, following an appeal, An Coimisin Pleanála has now overturned the council’s decision for Mayo Data Hub Ltd at Mullafarry and Tawnaghmore Upper, Killala.

The company behind the €1.5 billion development is Mayo Data Hub Ltd, which is part of US-based Avaio Digital.

The data centre – located 1.8km to the south of Killala and 10.5km to the north of Ballina – was to require 50MW average electrical power to operate.

The commission examined the case after retired scientist Colin Doyle, from Ennis, Co Clare, had lodged the third party objection.

Doyle had previously stated that his main concern was indirect greenhouse gas emissions (GHG) generated by the data centre and the resulting impact on climate.

Objector’s reaction

Speaking to The Journal, Doyle said he was “delighted” and hopes the decision “represents a change in thinking” around the environmental obligations of data centres in the planning process.

He has previously objected to other data centre projects, but insisted that it was important to do so, explaining that Ireland’s own climate targets may be in danger if further expansion takes place without safeguards.

Doyle added that he has faced criticism from local politicians in Mayo over his objection to the Killala data centre project. However, he said this was “crazy”, calling data centres a “national” and “worldwide” issue.

“I was objecting on climate impact and national targets. Wherever you live, we have to think as well of the cost if we keep adding in data centres with huge loads and diluting renewable portions of the grid,” Doyle said.

“It will hinder us on achieving our mandatory EU targets and see us hit with fines. If the politicians would like to pay those costs then well and good, but those costs will be spread out and come down to the taxpayer to pay, so we’re all going to be impacted.”

Political reaction

Reacting to the news, Fine Gael Senator Cathal Byrne said that while the government supports the expansion of data centres, he said it was important that operators have a “clear pathway” for 80% renewable energy use within six years of commencement.

Byrne told RTÉ Radio 1′s Late Debate show that this requirement was set down in the strategy for large-scale energy use for data centres.

Referring to the Mayo case, Byrne said: “The reason that application for planning permission was overturned was the fact that it was going to be fully provided with electricity off diesel generators and had no clear plan for how renewable energy was going to work.”

He added that the planning commission was “rightly” implementing the government’s policy by overturning the council’s original permission.

Planning body’s ruling

In the summary of its ruling, seen by The Journal, the planning commission said it completed an environmental impact assessment for the proposed development and concluded that the project relies to a large extent on the electricity sectoral ceilings being met.

It also required net-zero decarbonisation of Greenhouse Gas (GHG) emissions by 2050 as committed to in the Programme for Government and set out in the Climate Act 2021.

“It is considered the applicant has failed to demonstrate that the proposed development would be in accordance with the overarching objectives of the Climate Action Plan 2025,” An Coimisin Pleanála said.

The company had planned on having backup generators using fossil gas and biodiesel for the data centre.

While the commission noted there are a number of renewable wind energy projects near the site, it ruled that the developer had “not provided any evidence that the proposed development could avail of locally generated renewable power for the development and that there is sufficient capacity in the grid to service the development”.

It added that the project did not appear to have any long-term contract with a renewable energy supplier.

In an interview with the Western People local newspaper last year, Avaio Digital said that roughly 300 jobs were expected to be created during construction.

When complete, 30 to 35 full-time jobs were expected to man the data centre.

river - 2026-09-17T204548.072 Mayo resident Sally Rooney was one of the original objectors to the project Alamy Stock Photo Alamy Stock Photo

Meanwhile, in her own objection, Rooney told the council that she was making her submission “as a resident of County Mayo and a concerned citizen”, and urged the council to refuse planning permission for this “wasteful, unnecessary and environmentally toxic proposal”.

“Climate change represents an immediate and unprecedented threat to our way of life here in Mayo and to the future of human life around the world,” the Normal People and Intermezzo author said at the time.

View 60 comments
Comments Summary
AI-GENERATED
Readers debate whether data centres damage Ireland's electricity grid and economy
Where they land
Most welcome the decision to overturn the Mayo data centre
What they think
High data centre density strains the national grid and hikes consumer bills
Employment benefits are minimal compared to the resource drain
Close
60 Comments
This is YOUR comments community. Stay civil, stay constructive, stay on topic. Please familiarise yourself with our comments policy here before taking part.
Leave a Comment
    Submit a report
    Please help us understand how this comment violates our community guidelines.
    Thank you for the feedback
    Your feedback has been sent to our team for review.

    Leave a commentcancel

     
    JournalTv
    News in 60 seconds