Advertisement

We need your help now

Support from readers like you keeps The Journal open.

You are visiting us because we have something you value. Independent, unbiased news that tells the truth. Advertising revenue goes some way to support our mission, but this year it has not been enough.

If you've seen value in our reporting, please contribute what you can, so we can continue to produce accurate and meaningful journalism. For everyone who needs it.

File photo Electricity pylon via Shutterstock
Laois Kilkenny

Electricity project to be scrutinised at An Bord Pleanála hearings today

Hearings in Laois today are seen as a key test case for EirGrid’s Grid 25 project to update Ireland’s electricity infrastructure.

AN BORD PLEANÁLA is to hold its first public hearings on what is seen as a key test case for EirGrid’s plans to roll out electricity powerlines and substations across the country.

EirGrid, the body responsible for the development and maintenance of the State’s electricity grid, is constructing a number of large overground pylons for electricity lines as part of its countrywide EuroGrid 25 project to update Ireland’s electricity infrastructure.

A number of local groups have protested against the construction of the pylons with hearings in Portlaoise today, which will last for three days, focussing on the plans for an electricity substation in the Laois Kilkenny area, including the installation of over a dozen high-powered powerlines.

EirGrid argues that the project is justified because of quality and security of supply issues in the areas of Kilkenny, Carlow, Kildare and Loias.

“These problems are caused by the increase in load demand in the area over the last number of years , together with the growth in forecast demand in future,” the company says on its website.

“To alleviate these concerns, EirGrid has identified the proposed Laois-Kilkenny reinforcement scheme as the most efficient solution.

However, the Ratheniska, Timahoe and Spink Substation Action Group argues the project is too large and there is a lack of information from EirGrid about why such a large project is needed in the area.

WATCH: Mattie McGrath tells Rabbitte to ‘count the tits on Mrs Murphy’s cow’

Read: Eirgrid propose routes for €500mn Leinster-Munster high-voltage power line

Read: Putting North-South interconnector underground more expensive – report

Your Voice
Readers Comments
67
    Submit a report
    Please help us understand how this comment violates our community guidelines.
    Thank you for the feedback
    Your feedback has been sent to our team for review.